Don't overthink this.
Haha, I'm a micro manager. I'd rather get it all sorted in front of a computer screen so when 6m up in the air it is all relatively straightforward.
(Attachment Link)
Yes, I'm to, and also prepared my first install in the the same way, but what I have learned 6m high on the roof:
*Things don't always go as planned, dimensions are slightly off, brackets won't fit in a certain spot etc.
*Order some spare hardware, there is always a screw/bold that gets dropped/lost, a bracket that is bend or not properly coated etc.
*Elements are brutal up there, avoid the extremes (wind/rain/sun/temperature) at all costs.
Also, make sure you get mc4 connectors that are compatible with the ones that are supplied on the panels, being the exact same make and model or compatible together with the manufactures declaration that states they are, obviously only use the proper crimp-tool.
And you may need to bond the mounting rails to ground, again check your local codes.