(I'm not sure this is the right forum for this question, maybe Metrology or Test Equip would be better?)
I'm considering setting up an automated "stepped sine wave" measurement. The simplified process would be:
Set new frequency --> allow to settle --> trigger digitizer/DSO --> collect data --> rinse and repeat
What I'm concerned about is the synthesizer/generator frequency settling time. After sending the new frequency (via GPIB or whatever), how long does it take to make the change and settle? For sake of discussion, lets' assume "phase-continuous switching", where the new freq's first phase point will be calculated from the old freq's last phase point.
I looked through some generator data sheets and most companies don't specify it. They specify squarewave settling time but that is something else.
The only generator I have here that specifies it is an HP 3325B. It specifies switching time as the time from receipt of command to when the output freq is within 1Hz of the programmed value, as:
<10mS for a 100kHz step,
<25mS for a 1MHz step
<70mS for a 10MHz step.
Are there others that spec better?
How does one measure this?